J G Hale are still waiting for finalised designs etc to be able to make a full start on site, however you may have noticed that they have started to move some stone around site today, with their enabling works contractor to begin on site / compound set up, which will continue over the next few weeks, they are still hoping to have a physical start over the next few weeks.
Flooding
At the time of writing heavy rain is beginning to flow off the waterlogged site onto the junction of Broad Street and Devonshire Place.
A concern was raised at earlier meetings with Linc about the possibility of flooding on this junction.
No one was available on the site to discuss the flooding. I contacted Linc who had no one available to comment.
An email has been sent to J G Hale for comment.
UPDATE
Geraint at J G Hale has emailed to say the flooding has been remedied. It appears that leaves and debris had collected over the drain. The roads are now clear of standing water.